Trail & Sidewalk Projects

View the presentation from the 2024 bike/ped improvements meeting
View video from the 2024 bike/ped meeting:



We need your feedback on the Sudley Road Trail:
New 1.2 mile bike connection along Sudley Road between Godwin Drive and Grant Avenue
•    Alternatives:
  • Alternative A.1: 10’ shared use path on the west side of Sudley Road between Godwin Drive and Grant Avenue (Cost: $1.65 million)
  • Alternative A.2: 10’ shared use path on the west side of Sudley Road between Godwin Drive and Stonewall Road (Cost: $1.4 million)
  • Alternative E: 10’ shared use path on the west side of Sudley Road between Godwin Drive and Prince William Hospital and off-street bike lanes between Prince William Hospital and Grant Avenue  
  • Note: All concepts include bike lanes on Digges Road
Status:
  • This project is identified in the Bike Network Plan of the Comprehensive Plan
  • The concept was developed in August 2023
  • Project is currently unfunded

Share your comments/Take the survey
Cuéntenos su opinión llenando esta encuesta bilingüe.
Public input is being sought and is critical to receive before a project is recommended to be added to the Capital Improvement Program


How do these trails fit in with the Comprehensive Plan? View the Long Range Bike Plan
How do sidewalk projects fit in with the Comprehensive Plan? View the Pedestrian Network Plan 


Longstreet sidewalk - CopyLongstreet Sidewalk (T-84)
Constructing a sidewalk on the west side of Longstreet Drive between Grant Avenue and Weems Road.
This sidewalk is being built in concurrence with the Longstreet Drive Water Line project.
View the Current Design Plan

Status:
  • Final Design / Estimated Construction Start: Fall 2024
Contact: Mike Nicholson, Assistant Director of Water & Sewer


Wellington 2Wellington Road Shared Use Path Gap (T-88)
Constructing a shared-use path along Wellington Road from Nokesville Road to Prince William Street.
View the current design plan
Status:

Dumfries SidewalkDumfries Road Sidewalk (T-93)
Construct a sidewalk on the east side of Dumfries Road between Hastings Drive and Milic Street.
Status:
 Contact: Sung Jin Chung, Senior Engineer




Sudley Sidewalk map - CopySudley Road Sidewalk (T-94)
Constructing a sidewalk with a 6-foot buffer on the east side of Sudley Road between Grant Avenue and Mathis Avenue. The sidewalk will be 5 feet wide between Grant Avenue and Portner Avenue, and 6 feet wide between Portner Avenue and Mathis Avenue.
View the Concept Plan



Status:

  • Survey Notification Letters sent: 3/1/24
  • Field Survey began: 3/18/24
  • 10-Week Engineering Design Phase to begin: 5/6/2024
  • Community Meeting: TBD Summer 2024
Contact: Christer Carshult, Senior Engineer #703-257-8447

 